Osisko Drills More High Grades Across Windfall ... «Extended»

Full-scale construction of the processing plant is slated to take 18–24 months.

Once at steady state, the mine is projected to produce 300,000 ounces of gold annually . Key Metrics & Infrastructure Osisko drills more high grades across Windfall ...

The site is now fully powered by hydroelectricity through an 85km power line operated by the Cree First Nation of Waswanipi , significantly reducing the project's carbon footprint. Full-scale construction of the processing plant is slated

Final environmental approvals and a formal Board Investment Decision (FID) are expected in the second half of 2025 or early 2026. Osisko drills more high grades across Windfall ...

Recent infill results (February 2026) continue to show high-grade continuity, with some intercepts reaching average grades of 11.3 g/t Au in the measured category. Project Status and Path to Production